THE ESSENTIALS IN 30 SECONDS

  • ING is offering roughly $500 million of data-center loans at once through a bids-wanted-in-competition (BWIC) auction, Bloomberg first reported.
  • The 12 loans include a $25 million position tied to a Stargate data center in New Mexico, plus debt linked to Vantage Data Centers and CyrusOne.
  • Bids are due November 19 with a $10 million minimum; ING declined to comment to Reuters.

ING, the Dutch banking group, is trying to sell about $500 million of loans to data-center projects in a single auction, according to a Bloomberg report that Reuters and other outlets relayed this week. The bank declined to comment when Reuters contacted it.

What is on offer

The package contains a dozen loans and is being run as a bids-wanted-in-competition process, or BWIC, in which prospective buyers submit competing offers by a set deadline. Bids are due on November 19, and each must be for at least $10 million, the reports say.

The best-known item is a $25 million position in debt tied to a large New Mexico data center that forms part of Stargate, the AI infrastructure venture backed by OpenAI, SoftBank and Oracle. DatacenterDynamics identifies it as the Project Jupiter campus in Doña Ana County, a facility planned at up to 2.5 gigawatts and developed by Stack and BorderPlex Digital Assets. The portfolio also includes debt linked to data-center operators Vantage Data Centers and CyrusOne. The amounts and borrowers behind the remaining loans have not been reported.

DatacenterDynamics describes the deal as the first auction of this size made up only of data-center debt.

Why it matters

The auction surfaced as AI infrastructure stocks fell sharply after the US midterm elections on November 3, which raised expectations of tougher political scrutiny of data-center development. On November 5, shares of Applied Digital, Cipher Digital and IREN each dropped more than 14%, and International Business Times reports that the Nasdaq Composite lost more than 5%.

What it does and does not show

Banks sell loans routinely to free up capital, manage their balance sheets or trim exposure to a sector, and nothing reported so far suggests that the loans are in distress or that the underlying projects are failing. ING has not explained its reasons. The sale does show a lender choosing to reduce its exposure to AI data-center credit at a moment when the scale of borrowing behind the buildout is under growing scrutiny.

ING's own analysts wrote in an October research note that big technology firms could spend close to $1 trillion on capital expenditure in fiscal 2027, and that data-center operators would probably need continued access to debt markets to fund the expansion. How much buyers are willing to pay for the loans on November 19 should give a rough reading of market appetite for this kind of debt.